Nowra Sewerage Pump Stations

Name:

Nowra Sewerage Pump Stations

Client:

Shoalhaven Water

Value:

$3.2 M

Scope:

Construct a new sewage pump station from greenfield to commissioning.

  • Install secant pile wall for excavation
  • Excavate 8m to sub-base
  • FRP pump station
  • FRP manholes, valve pits
  • Install structural & mechanical equipment
  • Build a switchroom
  • Install electrical scop

Challenges:

  • Started excavation in Jan, 600mm of rain from Jan to March.
  • Extremely hard rock – had to use drilling and chemical fracturing.
  • “1 in 50” year rain events in one year. Passed all inspections from EPA re. dewatering.
  • Dewatering was a huge challenge

Status:

Ongoing