Construction of a new wastewater pump station SP1220 including:
- Wet Well structure (New SP1220)
- Filling old SP1210 Wet Well
- Emergency Storage Tank
- Inlet chamber
- Construction & installing
- Precast roof slabs
- Inlet maintenance hole(IMH)
- Connection of sewer services
- HDPE Liner (supply, install, weld and test)
- Demolition of piles and pile
- Capping beam
- Valve chamber
- Bypass bund
- Testing
|
|
- A very complex concrete structure.
- Construction works 16m below ground level.
- Access to multiple tanks up to 16m deep.
- Managing high risk activities inside a small work front including cranage, work at heights, plant operation, confined space and limited access areas.
- Construction of 60 pre-cast concrete elements up to 20T, delivery to site and installation utilizing 400T crane.
- Working with community housed immediately adjacent to construction site.
- Underground water management.
- Inclement weather, including two major flooding events.
|
|
- Completion of the project on time with high quality standards.
-
Completion of 10cm circular wet well at 16m height and 22m circumference, and emergency storage tank at 8m height.
|
|
300T of Reinforcement, 1500m3 of waterproof concrete.
|